The closest international TMX analogue is the United States' Mountain Valley Pipeline, also a ~10-year saga of court-driven delay, finished in June 2024 at US$7.85 B (CAD ~$22 M/km), that needed an Act of Congress to clear its final permits. Three of Canada's largest proposed pipelines (Northern Gateway, Energy East, and Keystone XL) sat in regulatory and political processes for 4 to 14 years before being cancelled without a single barrel moving. Over the same period the United States cancelled four of its own (Atlantic Coast, PennEast, Constitution, and Jordan Cove), three of them after a state withheld its water-quality certification. All figures on this page are capital construction cost in nominal dollars, converted to Canadian dollars at May 2026 exchange rates where required.
Recent built or under-construction pipelines, plotted four ways: capital cost per kilometre, calendar years per kilometre, cost overrun multiple against FID estimate, and capital cost against regulatory duration before construction. Toggle between the views below.
Recent built or under-construction pipelines, sorted ascending. Trans Mountain Expansion in red; other colours mark the tiers in the legend.
TMX's ~$35 M/km is between 5× and 7× the per-kilometre cost of comparable replacement and expansion work elsewhere in Canada, and roughly 5× the UAE West-East Pipeline's estimated $5–8 M/km. The closest Canadian peer is Coastal GasLink at $21.6 M/km. It is recent, crossed difficult terrain, and also ran well over budget.
All built or under-construction comparators sorted with TMX first, then by ascending capital cost per kilometre.
| Project | Country | Tier | Length (km) | Capacity | Build period | Final cost | Capital/km (CAD M) | Yrs/km |
|---|
Build period uses calendar years from the start of major civil works to in-service / mechanical completion. Pre-FID regulatory processing time is shown separately in the next section. UAE West-East Pipeline figures are estimated from disclosed EPC tranche values and trade-press reporting. ADNOC has not published a single project-level CAPEX number; flagged accordingly.
The bar below shows years from the date a project was first formally proposed or filed for regulatory review to either (a) the start of major civil works for built projects, or (b) the date of cancellation/rejection for killed projects. It is the single number for "time in the Canadian regulatory machine."
Built, cancelled, and stalled projects, sorted by years in process.
The four longest-running Canadian pipeline proposals never moved a barrel. Northern Gateway was in regulatory process for 14 years, Keystone XL and Mackenzie Valley for 13 each, and Eagle Spirit for 12 and counting. TMX, the one West Coast oil line that did get built, spent 6 years from its December 2013 application to the start of pipeline construction in December 2019. The UAE West-East Pipeline went from EPC contract award to ground-breaking in ~13 months.
Ten major pipelines cancelled in the last decade, plus one in limbo and one now under federal review. Sorted by years in process, longest first.
| Project | Country | Length (km) | Capacity | First proposed | Killed / status | Yrs in process | Cause of death (single sentence) |
|---|
"Yrs in process" measures the interval from initial formal proposal or regulatory filing to the date the project was abandoned, vetoed, or quashed by a court. For projects with no cancellation date (Eagle Spirit, in limbo since 2019, and Pacific Link, announced by Alberta in October 2025), the interval is measured to October 2026. Pacific Link is listed for reference and is not counted as cancelled or charted.
The 2013 Kinder Morgan filing estimated TMX at CAD 5.4 B. The final figure, reported by Trans Mountain's parent, the Canada Development Investment Corporation, and used by the Parliamentary Budget Officer in November 2024, is approximately CAD 34.2 B, a 6.3× nominal overrun. Trans Mountain Corporation's own cost updates name the drivers: high inflation and supply-chain problems, the November 2021 BC floods, unexpected archaeological discoveries, difficult terrain between Merritt and Hope, earthquake standards for the Burnaby Mountain tunnel, water-disposal costs on Sumas Prairie, and construction through densely populated areas between Sumas and Burnaby.
The US Mountain Valley Pipeline (Equitrans, 487 km, West Virginia to Virginia) finished June 2024 at US$7.85 B against a 2014 FID estimate of US$3.5 B, a 2.2× overrun and roughly CAD $22 M/km. MVP and TMX followed a similar path: ~10 years from filing to in-service, serial court-driven vacaturs of federal environmental permits (Fourth Circuit for MVP; Federal Court of Appeal for Northern Gateway and TMX), and rescue by extraordinary state action. MVP was saved by §324 of the Fiscal Responsibility Act of 2023 (an Act of Congress ratifying its permits and stripping the Fourth Circuit's jurisdiction); TMX was saved by the federal Crown purchase in 2018. Both were finished only after extraordinary action by the national government.
Coastal GasLink, the gas line from Dawson Creek to Kitimat that fed LNG Canada's first cargo in 2025, came in at CAD 14.5 B against a 2018 FID budget of CAD 6.2 B, a 2.3× overrun, comparable to MVP's. CGL is the closest cost-and-terrain analogue Canada has produced recently: greenfield, mountainous, contested, completed. Its $21.6 M/km matches MVP almost exactly and is roughly 60% of TMX. That gap (TMX 6.3× overrun versus CGL/MVP 2.2–2.3×) is the policy-relevant residual that points to TMX-specific drivers (Burnaby tunnel, federal-Crown ownership transition, financing carry on a forcibly extended schedule).
Texas intrastate gas (Gulf Coast Express, Permian Highway) delivered ~1,400 km of large-diameter pipe in under two years each, at CAD 3–4 M/km, with no FERC certificate required. Australia's Northern Gas Pipeline (Jemena, 622 km) was finished in 18 months at CAD 1.16 M/km. Europe's Baltic Pipe (Norway–Denmark–Poland) and Trans Adriatic Pipeline (Greece–Albania–Italy) crossed multiple sovereign borders and finished at CAD 3.4 M/km and CAD 7.6 M/km respectively. All four are democracies with environmental review. The two Texas lines needed no federal certificate because they never leave the state. Review still bites in Europe: Denmark's Environmental and Food Board of Appeal repealed Baltic Pipe's environmental permit in June 2021, and Energinet put the cost of the resulting delay at about €80 million.
In the United States, three of the four (Constitution, PennEast, and Pacific Connector/Jordan Cove) died after a state withheld its Clean Water Act §401 certification, even though federal regulators had approved them. The fourth, Atlantic Coast, was abandoned after repeated federal-court vacaturs of its permits. The Canadian four stopped at different points in the process. The Federal Court of Appeal quashed Northern Gateway's approval for inadequate consultation with First Nations, and the federal cabinet then rejected it. TC Energy withdrew Energy East after the National Energy Board widened its review to upstream and downstream emissions. Quebec, then Ottawa, rejected GNL Québec on greenhouse-gas grounds. The 2019 federal tanker moratorium closed Eagle Spirit's Prince Rupert terminus. Three further cancellations (Pacific NorthWest LNG, Mackenzie Valley, and Keystone XL) had different proximate causes: falling LNG prices, the US shale revolution, and a US Presidential Permit revocation. Three of the finished pipelines on this page needed exceptional action by the national government: the TMX Crown purchase, MVP's Act of Congress, and the January 2017 presidential memorandum that preceded Dakota Access's final federal easement at Lake Oahe. Coastal GasLink, also contested, was finished without it.
TMX cost about CAD 34.2 billion, 6.3 times its 2013 estimate. At roughly $35 million per kilometre, it ran between 5× and 7× comparable Canadian replacement and expansion work.
Cost basis. All cost figures are capital construction cost in nominal dollars. Figures in other currencies are converted to CAD at May 2026 Bank of Canada exchange rates (USD 1.38, EUR 1.48, AUD 0.90). No inflation adjustment is applied, so projects finished before 2024 are in the dollars of their completion year. That understates their cost relative to TMX in today's terms and narrows TMX's gap to older projects. TMX uses the CAD 34.2 B total project cost estimate in the Parliamentary Budget Officer's November 2024 report, which takes the figure from the 2023 annual report of Trans Mountain's parent, the Canada Development Investment Corporation. Coastal GasLink uses TC Energy's February 2023 final disclosure of ~CAD 14.5 B. Line 3 Canadian segment uses Enbridge's disclosed ~CAD 5.3 B for the Canadian portion only (the US segment is reported separately and faced different cost drivers). NGTL system expansion costs are CER filing values, not audited final figures (these are toll-recovered investments where final cost data is not always published outside the regulator's regulatory account).
UAE West-East Pipeline. ADNOC has not disclosed a single project-level CAPEX number. The USD 2–3 B estimate triangulates from the CPECC contract tranche values reported by Yicai Global (USD ~480 M for one section) and "multibillion-dollar" official language used in MEED and Upstream coverage. The 520 km length and ~50% completion figure as of 15–20 May 2026 are from CNBC, Al Jazeera, The National, and MEED. Pipeline & Gas Journal still reported the line as about half complete, with a 2027 target, in October 2026. Treat the per-km figure as inferred. It is the right order of magnitude but not audited.
US comparators. Mountain Valley Pipeline uses Equitrans' April 2024 8-K disclosure of US$7.85 B and Cardinal News reporting of the same figure; the FID baseline of US$3.5 B is from the 2014 FERC pre-file. The Mountain Valley Pipeline Act (§324 of the Fiscal Responsibility Act of 2023, P.L. 118-5, 3 Jun 2023) is the operative statute that ratified federal permits and stripped Fourth Circuit jurisdiction. Dakota Access uses USACE Omaha district disclosures of US$3.78 B for 1,886 km. Permian Highway and Gulf Coast Express use Kinder Morgan investor disclosures (US$2.0 B and US$1.75 B respectively); both are Texas intrastate lines requiring no FERC certificate, which is a material part of why they delivered in under two years. Cancelled US projects (ACP, PennEast, Constitution, Pacific Connector / Jordan Cove) report sunk-cost figures from sponsor 10-K filings and press releases; per-km values are not computed because no pipe was completed.
European and Australian comparators. Trans Adriatic Pipeline (TAP) cost from EIB project finance disclosures of €4.5 B for 878 km across Greece, Albania, and Italy; build period from TAP-AG's own timeline. Baltic Pipe (Norway–Denmark–Poland) cost from Gaz-System's FID disclosure (~€1.7 B) revised to ~€2.1 B at completion per European Commission launch reporting. Northern Gas Pipeline (Australia, Jemena) at AUD 800 M for 622 km from Tennant Creek to Mt Isa, per Jemena project page and AEMC register. Nord Stream 2 included as a context point for large-diameter offshore strategic pipelines: €9.5 B nominal, mechanically completed September 2021, never commissioned, sabotaged September 2022.
Years in regulatory process. For built projects: from formal regulatory filing (NEB application or equivalent) to the start of major civil works. For killed projects: from formal regulatory filing or first public proposal (whichever is earlier and verifiable) to the date of cancellation. Mackenzie Valley is measured from the Mackenzie Gas Project's 2004 application to the National Energy Board to its cancellation in December 2017 (13 years). An earlier proposal by a different consortium, Canadian Arctic Gas, went before the Berger Inquiry (appointed 1974, reported 1977) and is not counted.
Cost overrun multiples. Computed as final disclosed capital cost divided by the cost estimate at FID (or earliest binding cost estimate). TMX uses the 2013 Kinder Morgan filing as the FID baseline (CAD 5.4 B → CAD 34.2 B = 6.3×). CGL uses the 2018 FID budget (CAD 6.2 B → CAD 14.5 B = 2.3×). Line 3 uses the 2014 application figure (~CAD 4.9 B → CAD 5.3 B = 1.1×). Both ends are nominal and in each project's own currency, so a multiple includes general inflation between the estimate and completion. Over a build of about five years that inflation alone adds roughly 10–15% to the multiple.
What is not on this page. Lifecycle operating cost, tolls and rate of return to the federal Crown shareholder of Trans Mountain Corp, downstream refining capacity at tidewater, displacement effects on Canadian crude price differentials (the so-called "Western Canadian Select" discount), and GHG impact accounting are all material to a full pipeline policy review but are out of scope for this construction-cost benchmarking page.